Decision Maker: Executive Director of Economic Growth & Neighbourhood Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
This report sets out the decision for the
award of a new ‘Measured Term Contract’ (MTC) for the
provision of Electrical Repairs & Rewiring.
In addition, the report sets out the decision for the extension of
the current MTC for Electrical Testing for a further 2 years in
line with the contract conditions.
These contracts relate to the repair and maintenance of the
Council’s Housing stock.
No volume of expenditure is guaranteed under these contracts as
annual expenditure will depend on the actual level of work that is
required to be sub-contracted during the year. However, based on
expenditure records, typically the total expenditure on each
contract is estimated to be circa £300,000 and £70,000
respectively per annum.
It is the decision of the Director of Economic
Growth & Neighbourhood Services, in consultation with the Lead
Councillor for Housing, to award a new Measured Term Contract (MTC)
for Electrical Repairs and Rewiring for a period of 3 years from
1July 2020 till 30 June 2023 with a possible 2-year extension to
Shield Electrical Services Ltd, using the JCT Measured Term
Contract 2016.
It is the decision of the Director of Economic Growth &
Neighbourhood Services, in consultation with the Lead Councillor
for Housing, to extend the current contract with Pilon Ltd for
Electrical Testing for a further term of 2 years from 1 April 2020
till 31 March 2022 as provided within the original contract.
Publication date: 28/05/2020
Date of decision: 28/05/2020
Accompanying Documents: