Decision Maker: Executive Director of Economic Growth & Neighbourhood Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decisions set out in the book have been made
under delegated powers by the Chief Executive, Executive Directors
or the Chief Finance Officer and Monitoring Officer, in
consultation either with the relevant committee or Lead
Councillor.
This issue of the decision book will be in public circulation up
until Saturday 2 April 2022. During that period three Councillors
may request in writing to the Assistant Director of Legal and
Democratic Services that a decision should be referred either to a
committee, or to the Council (as appropriate) for formal
resolution.
The decision book is open to public inspection at the Civic Offices
between 9.00 am and 5.00 pm, Mondays to Fridays and can be accessed
on the Council’s website –
https://democracy.reading.gov.uk/mgListOfficerDecisions.aspx?bcr=1&BAM=0
The officer reports accompanying the decisions are attached.
Contact: Richard Woodford Committee Services
Tel: 0118 937 2332
e-mail: richard.woodford@reading.gov.uk
This report sets out the decision to include
additional carbon reduction measures to the works to construct the
new Rivermead Leisure Centre and new swimming pool at Palmer Park
using £976,248 from approved funds allocated for low carbon
capital investment works (energy efficiency and renewable energy
installations) in the MTFS. The work is to install additional air
source heat pumps (ASHPs) and solar panels to further improve the
carbon savings for the sites.
It is the decision of the Executive Director for Economic Growth
& Neighbourhood Services, in consultation with the Lead
Councillor for Strategic Environment, Planning and Transport and
the Lead Councillor for Health, Wellbeing and Sport, that
£976,248 of approved low carbon capital funds are deployed to
enable additional air source heat pumps and solar panels as part of
the works to build the new Rivermead leisure centre and new
swimming pool at Palmer Park Sports Stadium.
The existing contract including the annual revenue re-payment
schedule with Greenwich Leisure will be updated to include these
works to meet the agreed opening dates for the new facilities at
these sites.
Publication date: 23/03/2022
Date of decision: 23/03/2022
Accompanying Documents: